Flood Control and Drainage18CJ0006

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG TARLAC RIVER CONTROL (RIGHT DIKE), SAN LUIS SECTION, TARLAC CITY, TARLAC

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS REHABILITATION/IMPROVEMENT OF SLOPE PROTECTION ALONG TARLAC RIVER CONTROL (RIGHT DIKE), SAN LUIS SECTION, TARLAC CITY, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱18,599,512.76. Status: Reported complete (DPWH). Contractor on record: AZUL BUILDERS. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Slope Protection along Tarlac River Control (Right Dike), San Luis Section, Tarlac City, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-18-0013294

₱468,675,741.00 · FY2018

Released to Tarlac DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

73 projects · ₱1.9B total · 2 flags

4. Implementation

Contract Amount

₱18,599,512.76

Progress

Reported complete (DPWH)

Start Date

January 22, 2018

Target End

June 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.