Bridges19KE0049

WIDENING OF MAUBOG BRIDGE(B00027CG)ALONG CCR

WIDENING OF MAUBOG BRIDGE(B00027CG)ALONG CCR is a DPWH-tracked public work in Camiguin DEO, Region X. Reported contract value: ₱9,262,339.90. Status: Reported complete (DPWH). Contractor on record: JEJOR'S CONST CORP. Figures trace to dpwh.

Camiguin DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,262,339.90

Progress

Reported complete (DPWH)

Start Date

June 10, 2019

Target End

December 16, 2019

5. Audit