Flood Control and Drainage18FC0074

FLOOD MANAGEMENT PROGRAM, CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONST.

FLOOD MANAGEMENT PROGRAM, CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS; CONST. is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱19,011,776.28. Status: Reported complete (DPWH). Contractor on record: A C RIVERO DEVELOPMENT CORP 5122. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 5122

720 projects · ₱21.4B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BRIDGE, BARANGAY TALABAN, HIMAMAYLAN CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2021₱183.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS DAANG MAHARLIKA (LZ),K0356+076-K0357+377.00; K0357+406-K0357+894.00; K0357+920.00-K0358+819.00, CAMARINES NORTE 2ND LEGISLATIVE DISTRICT

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD WITH SEAWALL, BARANGAY TABA-TABA TO BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE, B

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS: JUBAN-MAGALLANES ROAD, JUBAN AND MAGALLANES, SORSOGON PROVINCE

Region V, Region V

2018₱139.7M
Reported complete (DPWH)
No sat.

CONST. OF CONCRETE ROAD - BRGY. SAN ANTONIO - CONDEZ - SAN LUIS - SAN VICENTE - FLORES ROAD LEADING

Region VI, Region VI

2017₱134.8M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CLUSTER V-I-REHABILITATION/IMPROVEMENT OF REVETMENT ALONG BARANGAY BAGACAY-PACO SECTION, BOTH SIDE

Region V, Region V

2021₱130.4M
Past target date (DPWH On-Going)
View all 720 projects →

4. Implementation

Contract Amount

₱19,011,776.28

Progress

Reported complete (DPWH)

Start Date

February 27, 2018

Target End

November 15, 2018

5. Audit