GAA 2016 MFO-315KE0089

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO SODA WATER SPRING

CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO SODA WATER SPRING is a DPWH-tracked public work in Camiguin DEO, Region X. Reported contract value: ₱27,965,753.42. Status: Reported complete (DPWH). Contractor on record: UKC BUILDERS INC. Figures trace to dpwh.

Camiguin DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 72%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation and Improvement of Calabanga Flood Control (Waterways), Brgy. Sabang - Salvacion Baybay - San Roque - San Pablo, Calabanga, Camarines Sur 3rd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027749

₱8,540,498.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱27,965,753.42

Progress

Reported complete (DPWH)

Start Date

August 16, 2016

Target End

February 2, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.