Roads23J00224

CONCRETING OF BRGY. ANAK JATI FMR, BRGY. ANAK JATI, MAIMBUNG, SULU

CONCRETING OF BRGY. ANAK JATI FMR, BRGY. ANAK JATI, MAIMBUNG, SULU is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱11,570,097.70. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ARADEL CONST AND SUPPLIES. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱11,570,097.70

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 18, 2023

Target End

September 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.