Buildings and Facilities23IB0125

CONSTRUCTION OF 1STY2CL, BALANGIGA CENTRAL ELEMENTARY SCHOOL, BALANGIGA, EASTERN SAMAR

CONSTRUCTION OF 1STY2CL, BALANGIGA CENTRAL ELEMENTARY SCHOOL, BALANGIGA, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱4,907,369.60. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: J R CONST SERVICES. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Poblacion, Hernani, Eastern Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Eastern Samar DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,907,369.60

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 10, 2023

Target End

December 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.