Buildings and Facilities20DF0059

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. TANZANG LUMA V, IMUS CITY; CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MAGDALO, IMUS CITY; RE

LOCAL PROGRAM-LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. TANZANG LUMA V, IMUS CITY; CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MAGDALO, IMUS CITY; RE is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱15,840,000.00. Status: Reported complete (DPWH). Contractor on record: R2A CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

95 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAMCONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONSTRUCTION OF WATERWAY ALONG IMUS RIVER,

Cavite 1st DEO, Region IV-A

2025₱116.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE FACILITY, IMUS CITY, CAVITE (PHASE 2)

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE FACILITY (IMUS PUBLIC MARKET), PHASE I, IMUS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGRAM CONST/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONST OF REVETMENT ALONG CAÑAS RIVER, BRGY SANTOL, PHASE V,TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIESCONCRETING OF DAANG HARI TO PATINDIG ARAW

Cavite 1st DEO, Region IV-A

2023₱67.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 4STY 20CL SCHOOL BUILDING AT CAYETANO TOPACIOELEMENTARY SCHOOL, IMUS CITY

Cavite 1st DEO, Region IV-A

2018₱60.2M
Reported complete (DPWH)
View all 95 projects →

4. Implementation

Contract Amount

₱15,840,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2020

Target End

October 9, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.