Construction of Flood Mitigation Structure22KC0030

Construction of Flood Control Structure along CDO City-Dominorog-Camp Kibaritan Road (Upstream & Downstream) of Tal-uban Bridge with Slope Protection, Sta. 0+000.00 - Sta. 0+420.00, Talakag, Bukidnon

Construction of Flood Control Structure along CDO City-Dominorog-Camp Kibaritan Road (Upstream & Downstream) of Tal-uban Bridge with Slope Protection, Sta. 0+000.00 - Sta. 0+420.00, Talakag, Bukidnon is a DPWH-tracked public work in TALAKAG (BUKIDNON), BUKIDNON, Region X. Reported contract value: ₱37,728,091.79. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to sumbong.

TALAKAG (BUKIDNON), BUKIDNON, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along CDO City-Dominorog-Camp Kibaritan Road (Upstream & Downstream) of Tal-uban Bridge with Slope Protection, Sta. 0+000.00 - Sta. 0+420.00, Talakag, Bukidnon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003101

₱100,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005650

₱20,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006789

₱10,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002956

₱357,414,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0004966

₱69,126.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0005743

₱27,369.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROX-22-0004965

₱670,697.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱37,728,091.79

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

March 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.