Buildings and Facilities18HE0069

COMPLETION/CONST./REPAIR/REHAB. OF MULTI-PURPOSE BUILDING, BARNAGAY LAWAAN, TALISAY CITY, CEBU

COMPLETION/CONST./REPAIR/REHAB. OF MULTI-PURPOSE BUILDING, BARNAGAY LAWAAN, TALISAY CITY, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱2,400,750.00. Status: Reported complete (DPWH). Contractor on record: DT&C CONST. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,400,750.00

Progress

Reported complete (DPWH)

Start Date

April 26, 2018

Target End

June 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.