Buildings and Facilities19DD0406

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BRGY. STA. CRUZ, ROSAR

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (DAY CARE CENTER), BRGY. STA. CRUZ, ROSAR is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱5,879,870.00. Status: Reported complete (DPWH). Contractor on record: VRV CONST AND TRADING. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-19-0014483

₱60,000.00 · FY2019

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

19DD0406

₱5,703,600.00 · VRV CONSTRUCTION AND TRADING

Contractor

195 projects · ₱2.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), PADRE GARCIA COMMUNITY HOSPITAL, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2021₱96.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BOLBOK INTEGRATED NATIONAL HIGH SCHOOL, BARANGAY BOLBOK, LIPA CITY, BATA

Batangas 4th DEO, Region IV-A

2024₱78.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TALISAY, LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱57.6M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION/ COMPLETION OF MULTI-PURPOSE BUILDING (COMMUNITY HOSPITAL) AT BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MAXIMO T. HERNANDEZ MEMORIAL NATIONAL HIGH SCHOOL AND MALAININ ELEMENTARY SCHOOL, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.4M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM, CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/ FACILITIES, CONSTRUCTION OF MULTI- PURPOSE BUILDING (BUREAU OF FIRE), LIPA CITY, BATANGAS

Batangas 4th DEO, Region IV-A

2020₱38.0M
Reported complete (DPWH)
View all 195 projects →

4. Implementation

Contract Amount

₱5,879,870.00

Progress

Reported complete (DPWH)

Start Date

August 12, 2019

Target End

December 9, 2019

5. Audit