GAA 2020 OO-220DF0012

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJORFLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF REVETMENT ALONG IMUS RIVER,

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJORFLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF REVETMENT ALONG IMUS RIVER, is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱9,799,995.14. Status: Reported complete (DPWH). Contractor on record: D C R CONST. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,799,995.14

Progress

Reported complete (DPWH)

Start Date

February 13, 2020

Target End

July 11, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.