Buildings and Facilities22OE0141

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 149 ZONE 13, MANILA CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 149 ZONE 13, MANILA CITY is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱19,796,785.10. Status: Reported complete (DPWH). Contractor on record: AL-AMEN BUILDERS. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Facilities along Earnshaw St., (Estero de San Miguel to A.H. Lacson Ave.) and Antipolo St., (G. Tuazon to Espana Blvd.), Manila City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

North Manila DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

74 projects · ₱1.8B total · 0 flags

Other projects by this contractor

No sat.

INSTALLATION OF SOLAR LED STREETLIGHTS WITHIN BARANGAYS 649 TO 828, PRES. QUIRINO AVE (FROM TAFT AVE. TO SOUTH SUPERHIGHWAY), SOUTH SUPERHIGHWAY (FROM ZOBEL ROXAS ST. TO P. QUIRINO AVE), P. FAURA ST. (SAN MARCELINO ST. TO ROXAS BLVD.), ESCODA ST. (FROM TA

South Manila DEO, National Capital Region

2025₱145.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE OF ESTERO DE PACO, MANILA CITY PHASE 2

South Manila DEO, National Capital Region

2025₱143.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE OF ESTERO DE PACO, MANILA CITY PHASE 1

South Manila DEO, National Capital Region

2025₱143.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 1), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 2), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 3), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
View all 74 projects →

4. Implementation

Contract Amount

₱19,796,785.10

Progress

Reported complete (DPWH)

Start Date

February 23, 2022

Target End

December 19, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.