Construction of Flood Mitigation Structure22OG0084

Construction of Retaining Wall at Libis Elementary School (Phase 1), Barangay Libis, Quezon City

Construction of Retaining Wall at Libis Elementary School (Phase 1), Barangay Libis, Quezon City is a DPWH-tracked public work in QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region. Reported contract value: ₱24,733,928.89. Status: Reported complete (DPWH). Contractor on record: SONPRO CONST. Figures trace to sumbong.

QUEZON CITY (METROPOLITAN MANILA), QUEZON CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Sauyo, Quezon City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003130

₱960,579,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009346

₱30,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0007146

₱20,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003019

₱12,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱24,733,928.89

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

April 15, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.