Buildings and Facilities16D00062

CONSTRUCTION OF EVACUATION CENTER BRGY. PANIKIHAN/BUENSUCESO, GUMACA, QUEZON

CONSTRUCTION OF EVACUATION CENTER BRGY. PANIKIHAN/BUENSUCESO, GUMACA, QUEZON is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱34,337,410.02. Status: Reported complete (DPWH). Contractor on record: EXCELSIUS ENGINEERING SERVICES. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱34,337,410.02

Progress

Reported complete (DPWH)

Start Date

July 7, 2017

Target End

March 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.