Buildings and Facilities25OE0159

REHABILITATION OF MULTI-PURPOSE BUILDING, PHASE IV, WITHIN ZONE 58 TO 67, MANILA CITY

REHABILITATION OF MULTI-PURPOSE BUILDING, PHASE IV, WITHIN ZONE 58 TO 67, MANILA CITY is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱48,654,089.75. Status: Past target date (DPWH On-Going). Contractor on record: 525 CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Sunog Apog, Barangay 172, Manila City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

North Manila DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,654,089.75

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

December 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.