GAA 2024 OO-124P00013

CONSTRUCTION OF MISSING LINKS/NEW ROADS - BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, ASIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), BENGUETSABLAN, BENGUET

CONSTRUCTION OF MISSING LINKS/NEW ROADS - BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, ASIN - NANGALISAN JCT. - BAYABAS - MONGLO JCT. (SECTION 1 OF BLISTT OUTER RING CIRCUMFERENTIAL ROAD), BENGUETSABLAN, BENGUET is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱38,600,000.00. Status: Past target date (DPWH On-Going). Contractor on record: UNIVERSAL DE LEON CONST AND AGGREGATES. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

92 projects · ₱6.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS / NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B OF BLIS

Cordillera Administrative Region, Cordillera Administrative Region

2021₱241.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL ALONG AGNO RIVER, SITIO BANAO AND SITIO ADONOT, BARANGAY AMBUKLAO, BOKOD, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2024₱147.6M
Past target date (DPWH On-Going)
No sat.

SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SAGPAT, KIBUNGAN, BENGUET TO SANTOL, LA UNION ROAD (PHASE II), KIBUNGAN, BENGUET

Benguet 2nd DEO, Cordillera Administrative Region

2024₱147.6M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ALONG CONG. ANDRES ACOP COSALAN RD (S00379LZ) K0340+1361 - K0340+1477, KABAYAN, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱125.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGNO RIVER MAIN STREAM (BANAO SECTION), BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱120.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - ALONG CONG. ANDRES ACOP COSALAN RD (S00386LZ) K0316+375 - K0316+528, BOKOD, BENGUET

Benguet 1st DEO, Cordillera Administrative Region

2024₱120.6M
Reported complete (DPWH)
View all 92 projects →

4. Implementation

Contract Amount

₱38,600,000.00

Progress

Past target date (DPWH On-Going)

Start Date

March 14, 2024

Target End

April 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.