Buildings and Facilities17EB0141

CLUSTER 2017BEFF-03: CONST. OF CLASSROOMS (BATCH 12): A) FILOMENO JIMENEZ MS, 1STY3CL, B) NEW DAGUPAN ES, 1STY2CL, CALINTAAN, OCC. MINDORO

CLUSTER 2017BEFF-03: CONST. OF CLASSROOMS (BATCH 12): A) FILOMENO JIMENEZ MS, 1STY3CL, B) NEW DAGUPAN ES, 1STY2CL, CALINTAAN, OCC. MINDORO is a DPWH-tracked public work in Mindoro Occidental DEO, Region IV-B. Reported contract value: ₱7,193,020.80. Status: Reported complete (DPWH). Contractor on record: AGATHA CHRISTIE TRADING AND CONST. Figures trace to dpwh.

Mindoro Occidental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lumintao Flood Control (Tanyag Section - Phase 2), Calintaan, Occidental Mindoro
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Mindoro Occidental DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱7,193,020.80

Progress

Reported complete (DPWH)

Start Date

January 29, 2018

Target End

July 15, 2018

5. Audit