Roads17J00127

ROAD WIDENING OF JOLO INDANAN PARANG SILANGKAN ROAD, SULU (1ST DEO), STA. 09+000.00 TO STA. 13+840.00, NET LENGTH: 9.68 LANE KM

ROAD WIDENING OF JOLO INDANAN PARANG SILANGKAN ROAD, SULU (1ST DEO), STA. 09+000.00 TO STA. 13+840.00, NET LENGTH: 9.68 LANE KM is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱139,576,701.10. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱139,576,701.10

Progress

Reported complete (DPWH)

Start Date

February 6, 2018

Target End

September 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.