Flood Control and Drainage22DN0067

CONSTRUCTION OF SLOPE PROTECTION RETAINING WALL HORNO CREEK (PHASE 2), BARANGAY SAN ROQUE, ANTIPOLO CITY (SECOND DISTRICT)

CONSTRUCTION OF SLOPE PROTECTION RETAINING WALL HORNO CREEK (PHASE 2), BARANGAY SAN ROQUE, ANTIPOLO CITY (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱9,899,566.96. Status: Reported complete (DPWH). Contractor on record: T E TRINIDAD CONST. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pulang Panyo to Binayoyo (Phase 3), Brgy. San Jose, Antipolo City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Rizal 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

79 projects · ₱1.0B total · 0 flags

Other projects by this contractor

View all 79 projects →

4. Implementation

Contract Amount

₱9,899,566.96

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

June 23, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.