Flood Control and Drainage17DH0003

CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN/BALANAC RIVER, BRGY. MAULAWIN, PAGSANJAN, LAGUNA, 4TH LD

CONSTRUCTION OF RIVER CONTROL ALONG PAGSANJAN/BALANAC RIVER, BRGY. MAULAWIN, PAGSANJAN, LAGUNA, 4TH LD is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱28,935,332.40. Status: Reported complete (DPWH). Contractor on record: PROTECH CONST & DEVELOPMENT CORP FORMERLY. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Upstream and Downstream) along Buenavista River, Nagcarlan, Laguna
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0013804

₱130,490.00 · FY2017

Released to Tarangnan National Sa High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

25 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱28,935,332.40

Progress

Reported complete (DPWH)

Start Date

June 9, 2017

Target End

February 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.