Flood Control and Drainage18CM0044

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENT OF CABALAN RIVER, OLONGAPO CITY

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, IMPROVEMENT OF CABALAN RIVER, OLONGAPO CITY is a DPWH-tracked public work in Zambales 2nd DEO, Region III. Reported contract value: ₱46,559,589.04. Status: Reported complete (DPWH). Contractor on record: JAMJLE PROPERTIES SUBIC AND DEVELOPMENT CORPORAT. Figures trace to dpwh.

Zambales 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Cabalan River, Olongapo City, Zambales
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0022785

₱0.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱46,559,589.04

Progress

Reported complete (DPWH)

Start Date

March 15, 2018

Target End

September 30, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.