GAA 2025 OO-225FG0047

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY SAN ISIDRO, TINAMBAC, CAMARINES SUR

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARANGAY SAN ISIDRO, TINAMBAC, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱18,995,559.99. Status: Past target date (DPWH On-Going). Contractor on record: E A SANCHO CONST INC FORM E A SANCHO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Barangay San Isidro, Tinambac, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Sur 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

113 projects · ₱3.8B total · 0 flags

Other projects by this contractor

View all 113 projects →

4. Implementation

Contract Amount

₱18,995,559.99

Progress

Past target date (DPWH On-Going)

Start Date

June 20, 2025

Target End

December 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.