Flood Control and Drainage18CK0024

SLOPE PROT./EROSION CONTROL (R/S) ALONG O'DONNELL RIVER (PARADE GROUND SECT., AREA 2, CROW VALLEY RE

SLOPE PROT./EROSION CONTROL (R/S) ALONG O'DONNELL RIVER (PARADE GROUND SECT., AREA 2, CROW VALLEY RE is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱9,278,742.12. Status: Reported complete (DPWH). Contractor on record: JAM-C BUILDERS 32870. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,278,742.12

Progress

Reported complete (DPWH)

Start Date

February 1, 2018

Target End

May 14, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.