Buildings and Facilities16LH0048

COMPLETION OF MULTI-PURPOSE BUILDING AT BRGY. SIRAWAN, TORIL DISTRICT, DAVAO CITY

COMPLETION OF MULTI-PURPOSE BUILDING AT BRGY. SIRAWAN, TORIL DISTRICT, DAVAO CITY is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱494,396.47. Status: Reported complete (DPWH). Contractor on record: DECKTOP BUILDERS CORP FORMERLY: DAVAO ENGI 30944. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱494,396.47

Progress

Reported complete (DPWH)

Start Date

April 12, 2016

Target End

June 10, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.