Flood Control and Drainage25DH0040

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. CRUZ LAKESHORE, STA. CRUZ, LAGUNA

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG STA. CRUZ LAKESHORE, STA. CRUZ, LAGUNA is a DPWH-tracked public work in Laguna 1st DEO, Region IV-A. Reported contract value: ₱93,598,782.56. Status: Past target date (DPWH On-Going). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Laguna 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Calangay River), Sta. Maria RIS, Sta. Maria, Laguna
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Laguna 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱93,598,782.56

Progress

Past target date (DPWH On-Going)

Start Date

August 21, 2025

Target End

August 6, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.