Flood Control and Drainage18EG0048

CONSTRUCTION OF FLOOD CONTROL AND MITIGATION STRUCTURE ALONG BRGY. STA. MONICA, K0005+814.80 - K0006+304.80, PUERTO PRINCESA SOUTH ROAD, PUERTO PRINCESA CITY

CONSTRUCTION OF FLOOD CONTROL AND MITIGATION STRUCTURE ALONG BRGY. STA. MONICA, K0005+814.80 - K0006+304.80, PUERTO PRINCESA SOUTH ROAD, PUERTO PRINCESA CITY is a DPWH-tracked public work in Palawan 3rd DEO, Region IV-B. Reported contract value: ₱4,759,460.28. Status: Reported complete (DPWH). Contractor on record: HARDROCKPLATINUM DEVELOPMENT CORP. Figures trace to dpwh.

Palawan 3rd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Mitigation Structure along Bgy Sta. Monica, Puerto Princesa South Road
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-18-0005523

₱0.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,759,460.28

Progress

Reported complete (DPWH)

Start Date

May 3, 2018

Target End

August 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.