Buildings and Facilities16CN0136

CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING, DINIOG NATIONAL HIGH SCHOOL, DILASAG, AURORA

CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING, DINIOG NATIONAL HIGH SCHOOL, DILASAG, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱1,976,524.56. Status: Reported complete (DPWH). Contractor on record: RADIANCE TRADERS. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,976,524.56

Progress

Reported complete (DPWH)

Start Date

March 5, 2017

Target End

May 28, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.