Buildings and Facilities19GN0031

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ZAMORA, PONTEVEDRA, NEGROS OCCIDENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. ZAMORA, PONTEVEDRA, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱2,880,892.61. Status: Reported complete (DPWH). Contractor on record: ONE TERRA BUILDERS AND CONST SUPPLY 40848. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 40848

86 projects · ₱664.8M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - JCT. PONTEVEDRA - LA CASTELLANA ROAD - K0046+000 - K0047+500

Negros Occidental 4th DEO, Negros Island Region

2024₱53.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0042+600 - K0045+862, K0045+920 - K0045+962

Negros Occidental 4th DEO, Negros Island Region

2024₱30.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION RECONSTRUCTION UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT. PONTEVEDRA-LA CASTELLANA ROAD, K0045+(-975) -K0045+436, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2020₱26.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0040+(-664) - K0040+575, K0040+585 - K0041+230, K0041+272 - K0042+600

Negros Occidental 4th DEO, Negros Island Region

2025₱25.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REINFORCED CONCRETE DECK GIRDER (RCDG) BRIDGE INCLUDING APPROACHES AND SIDE SLOPE PROTECTION AT BRGY. CANROMA TO SITIO SUA TRINIDAD ROAD, BRGY. DON SALVADOR BENEDICTO, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2023₱24.7M
Reported complete (DPWH)
No sat.

RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. PONTEVEDRA - LA CASTELLANA ROAD, K0045+436 - K0046+545, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2021₱21.7M
Reported complete (DPWH)
View all 86 projects →

4. Implementation

Contract Amount

₱2,880,892.61

Progress

Reported complete (DPWH)

Start Date

June 4, 2019

Target End

September 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.