Flood Control and Drainage20GO0105

CONSTRUCTION OF REVETMENT WITH FLOODWALL ALONG SUM-AG RIVER, BACOLOD CITY

CONSTRUCTION OF REVETMENT WITH FLOODWALL ALONG SUM-AG RIVER, BACOLOD CITY is a DPWH-tracked public work in Bacolod City DEO, Negros Island Region. Reported contract value: ₱38,600,000.00. Status: Reported complete (DPWH). Contractor on record: SILVER DRAGON CONST. Figures trace to dpwh.

Bacolod City DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-19-0021191

₱246,816.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱38,600,000.00

Progress

Reported complete (DPWH)

Start Date

September 28, 2020

Target End

May 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.