Flood Control and Drainage23M00002

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PULANGI RIVER, BARANGAY NABUNDAS SECTION - PHASE II, STA. 001+500-STA. 001+755.5, PIKIT, COTABATO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PULANGI RIVER, BARANGAY NABUNDAS SECTION - PHASE II, STA. 001+500-STA. 001+755.5, PIKIT, COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱98,077,803.65. Status: Past target date (DPWH On-Going). Contractor on record: THREE W BUILDERS INC 10722. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱98,077,803.65

Progress

Past target date (DPWH On-Going)

Start Date

August 18, 2023

Target End

May 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.