Buildings and Facilities17GE0138

CONSTRUCTION OF SCHOOL BUILDINGS UNDER 2017 BEFF (BATCH 3) COMPLETION OF TWO STOREY 10 CL G.I. ROOF SCHOOL BUILDING, SUPANG NATIONAL HIGH SCHOOL

CONSTRUCTION OF SCHOOL BUILDINGS UNDER 2017 BEFF (BATCH 3) COMPLETION OF TWO STOREY 10 CL G.I. ROOF SCHOOL BUILDING, SUPANG NATIONAL HIGH SCHOOL is a DPWH-tracked public work in Guimaras DEO, Region VI. Reported contract value: ₱1,944,090.47. Status: Reported complete (DPWH). Contractor on record: ALJ CONST AND SUPPLY 30571. Figures trace to dpwh.

Guimaras DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,944,090.47

Progress

Reported complete (DPWH)

Start Date

December 22, 2017

Target End

March 21, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.