Roads17K00017

COMPLETION OF THE EAST WEST LATERAL RD CONNCETING AGUSAN DEL SUR TO BUK JCT. CDO CITY CAMP KIBARITAN

COMPLETION OF THE EAST WEST LATERAL RD CONNCETING AGUSAN DEL SUR TO BUK JCT. CDO CITY CAMP KIBARITAN is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱77,578,178.53. Status: Reported complete (DPWH). Contractor on record: LEXAND CONST & DEVELOPMENT 39573. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱77,578,178.53

Progress

Reported complete (DPWH)

Start Date

March 2, 2017

Target End

May 12, 2018

5. Audit