Flood Control and Drainage24FE0070

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER (UPSTREAM, LEFTSIDE), BARANGAY BALIUAG VIEJO, MINALABAC, CAMARINES SUR

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BICOL RIVER (UPSTREAM, LEFTSIDE), BARANGAY BALIUAG VIEJO, MINALABAC, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱47,767,729.67. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: BICOL GOLDROCK CONST CORP. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Burabod Creek, Tigaon, Camarines Sur
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Camarines Sur 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

253 projects · ₱14.5B total · 12 flags

Other projects by this contractor

No sat.

CLUSTER I-ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-I-A: REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-CATANDUANES CIR RD-K0028+000-K0028+647, K0028+788-K0029+000, K

Catanduanes DEO, Region V

2025₱218.7M
Ongoing (DPWH-reported)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BICOL RIVER FLOOD MITIGATION STR

Region V, Region V

2024₱148.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)PASACAO-BALATAN TOURISM COASTAL HIGHWAY, PASACAO, CAMARINES SUR, PACKAGE 3, CAMARINES SUR(2N

Region V, Region V

2022₱144.8M
Reported complete (DPWH)
No sat.

CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - SAN ISIDRO-BAHAO ROAD LEADING TO BAHAO PORT, LIBMANAN, CAMARINES SUR, PACKAGE C

Camarines Sur 2nd DEO, Region V

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ROAD, TAGBAC, RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱139.6M
Past target date (DPWH On-Going)

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG LIBMANAN RIVER (RIGHT SIDE) WITHIN BICOL RIVER BASIN, BARANGAY MA

Camarines Sur 2nd DEO, Region V

2024₱135.1M
Reported complete (DPWH)
View all 253 projects →

4. Implementation

Contract Amount

₱47,767,729.67

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 24, 2025

Target End

November 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.