Roads20IG0086

CONCRETING OF BRGY. CABULISAN TO BRGY. CAMINTO FMR, BRGY. CABULISAN AND CAMINTO, INOPACAN, LEYTE

CONCRETING OF BRGY. CABULISAN TO BRGY. CAMINTO FMR, BRGY. CABULISAN AND CAMINTO, INOPACAN, LEYTE is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱9,641,400.00. Status: Reported complete (DPWH). Contractor on record: C N E CONST 22148. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,641,400.00

Progress

Reported complete (DPWH)

Start Date

March 4, 2021

Target End

May 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.