Water Provision and Storage25BK0098

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM A. LIGAYA ELEMENTARY SCHOOL B. DUMABEL INTEGRATED SCHOOL C. PINARIPAD NATIONAL HIGH SCHOOL D. VICTORIA HIGH SCHOOL E. DUNGO BRGY. OFFICE F. POTIA ELEMENTARY SCHOOL G. LUMAGUI ELEMENTARY

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM A. LIGAYA ELEMENTARY SCHOOL B. DUMABEL INTEGRATED SCHOOL C. PINARIPAD NATIONAL HIGH SCHOOL D. VICTORIA HIGH SCHOOL E. DUNGO BRGY. OFFICE F. POTIA ELEMENTARY SCHOOL G. LUMAGUI ELEMENTARY is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱2,526,040.70. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JHUERS CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Downstream (Villa Sur Section), Maddela, Quirino
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quirino DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

32 projects · ₱266.9M total · 0 flags

Other projects by this contractor

No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG CORDON - AURORA BDRY RD (ISABELA BDRY - JCT DUMABATO) - KO339+000 - K0345+338, CABARROGUIS AND AGLIPAY,

Quirino DEO, Region II

2025₱29.3M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF RIVER FLOOD CONTROL AT NALUNGTUTAN BRIDGE (SAN DIONISIO II SECTION), NAGTIPUNAN, QUIRINO

Quirino DEO, Region II

2025₱28.1M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MADDELA DISTRICT HOSPITAL, MADDELA, QUIRINO

Quirino DEO, Region II

2024₱19.8M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG ECHAGUE - JONES - MADDELA RD (VILLA NORTE - PANANG SECT) - K0377+(-859) - K0380+298, MADDELA, QUIRINO

Quirino DEO, Region II

2025₱19.5M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG MANGANDINGAY - SAGUDAY ISABELA BDRY RD - K0336+(-310) - K0340+334, DIFFUN AND SAGUDAY, QUIRINO

Quirino DEO, Region II

2025₱19.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF THE LEGISLATIVE BUILDING IN THE MUNICIPALITY OF DIADI, PROVINCE OF NUEVA VIZCAYA

Nueva Vizcaya DEO, Region II

2025₱19.2M
Past target date (DPWH On-Going)
View all 32 projects →

4. Implementation

Contract Amount

₱2,526,040.70

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 29, 2025

Target End

August 31, 2025