Flood Control and Drainage25DQ0023

CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY SAN NICOLAS 1, BACOOR CITY, CAVITE

CONSTRUCTION OF DRAINAGE STRUCTURE, BARANGAY SAN NICOLAS 1, BACOOR CITY, CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱14,848,245.25. Status: Past target date (DPWH On-Going). Contractor on record: T E TRINIDAD CONST. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures and Other Improvements At Molino River at Barangays Molino 6 to San Nicolas 1, Bacoor City, Cavite
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cavite 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

79 projects · ₱1.0B total · 0 flags

Other projects by this contractor

View all 79 projects →

4. Implementation

Contract Amount

₱14,848,245.25

Progress

Past target date (DPWH On-Going)

Start Date

February 17, 2025

Target End

August 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.