Construction of Flood Mitigation Structure24HO0122

Construction of Revetment Wall along Talaba River Flood Control, Barangay Canduling, Ronda, Cebu

Construction of Revetment Wall along Talaba River Flood Control, Barangay Canduling, Ronda, Cebu is a DPWH-tracked public work in RONDA (CEBU), CEBU, Region VII. Reported contract value: ₱39,196,415.80. Status: Reported complete (DPWH). Contractor on record: FIRST GRANDEUR BUILDERS. Figures trace to sumbong.

RONDA (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment Wall along Talaba River Flood Control, Barangay Canduling, Ronda, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0011357

₱1,326,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0011359

₱122,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱39,196,415.80

Progress

Reported complete (DPWH)

Start Date

April 1, 2024

Target End

October 18, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.