Bridges15IB0278

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES AT MALINAO BRIDGE (B00515SM) ALONG JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD, EASTERN SAMAR

REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES AT MALINAO BRIDGE (B00515SM) ALONG JCT. TAFT - ORAS - SAN POLICARPO - ARTECHE ROAD, EASTERN SAMAR is a DPWH-tracked public work in Eastern Samar DEO, Region VIII. Reported contract value: ₱6,840,020.57. Status: Reported complete (DPWH). Contractor on record: TUBIGAN BUILDERS 33185. Figures trace to dpwh.

Eastern Samar DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱6,840,020.57

Progress

Reported complete (DPWH)

Start Date

February 2, 2016

Target End

April 11, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.