Water Provision and Storage21G00206

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAINWATER COLLECTOR SYSTEM is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱4,516,894.92. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: S T SALCEDO CONST CORP FORMERLY: SHAK CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,516,894.92

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

November 10, 2022

Target End

February 26, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.