Flood Control and Drainage19D00044

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MNGMT. PROGRAM CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM CONSTRUCTION OF ROAD DIKE/RIVER BANK PROTECTION, BRGY. GAHAK (EAST SIDE), PHASE 3, KAWIT, CAVITE

PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MNGMT. PROGRAM CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM CONSTRUCTION OF ROAD DIKE/RIVER BANK PROTECTION, BRGY. GAHAK (EAST SIDE), PHASE 3, KAWIT, CAVITE is a DPWH-tracked public work in Region IV-A, Region IV-A. Reported contract value: ₱58,942,189.50. Status: Reported complete (DPWH). Contractor on record: HONEYVILLECONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Region IV-A, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱6.0B total · 0 flags

4. Implementation

Contract Amount

₱58,942,189.50

Progress

Reported complete (DPWH)

Start Date

July 22, 2019

Target End

June 30, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.