Construction of Flood Mitigation Structure24DI0022

Construction of River Protection Structure at Sta. Rosa River, near Coca Cola, Sta. Rosa City, Laguna

Construction of River Protection Structure at Sta. Rosa River, near Coca Cola, Sta. Rosa City, Laguna is a DPWH-tracked public work in CITY OF SANTA ROSA (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱47,946,089.10. Status: Reported complete (DPWH). Contractor on record: 11 DIAMOND EAGLE CONST CORP FORMERLY:11 DIAMOND EAGLE CONST. Figures trace to sumbong.

CITY OF SANTA ROSA (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Structure Phase 3, ( Biñan - Sta. Rosa Boundary ) , Biñan Side, Biñan City, Laguna
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0014120

₱300,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008420

₱1,398,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0000315

₱274,684.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0008421

₱129,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-24-0006893

₱78,562.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱47,946,089.10

Progress

Reported complete (DPWH)

Start Date

February 26, 2024

Target End

October 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.