Roads22CJ0240

CONCRETING OF PUROK 4, BRGY. CABANABAAN TO BRGY. TAGUIPORO FMR, BRGY. CABANABAAN AND BRGY. TAGUIPORO, CAMILING, STA. IGNACIA, TARLAC

CONCRETING OF PUROK 4, BRGY. CABANABAAN TO BRGY. TAGUIPORO FMR, BRGY. CABANABAAN AND BRGY. TAGUIPORO, CAMILING, STA. IGNACIA, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱11,940,000.00. Status: Reported complete (DPWH). Contractor on record: T2B3 BUILDERS AND SUPPLIES CORP. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Camiling River (Left Bank), Libueg-Bacabac Section (Package D), Sta. 0+000 - Sta. 0+362, Camiling, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Tarlac DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,940,000.00

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

August 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.