GAA 2018 OO-218LB0042

INSTALLATION OF GABIONS AND MATTRESSES ALONG BAGO RIVER, KALIRAYA SECTION STA. 1+044-STA. 1+587, STA

INSTALLATION OF GABIONS AND MATTRESSES ALONG BAGO RIVER, KALIRAYA SECTION STA. 1+044-STA. 1+587, STA is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱48,995,658.95. Status: Reported complete (DPWH). Contractor on record: ALZAM ENT INC FORMERLY: ALZAM ENT. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Installation of Gabions and Mattresses along Bago River, Kaliraya Section, Sta. 1+008 - Sta. 1+587, Sta. 1+593 - Sta. 1+702 Left Bank, Davao City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-LGRCB-18-0025292

₱50,900,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,995,658.95

Progress

Reported complete (DPWH)

Start Date

June 3, 2018

Target End

January 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.