Bridges23G00044

BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SECTION 1, SEGMENT 3, PHASE 4, TALISAY CITY, NEGROS OCCIDENTAL

BACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SECTION 1, SEGMENT 3, PHASE 4, TALISAY CITY, NEGROS OCCIDENTAL is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱67,667,693.00. Status: Past target date (DPWH On-Going). Contractor on record: A C RIVERO DEVELOPMENT CORP. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

736 projects · ₱22.2B total · 19 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BRIDGE, BARANGAY TALABAN, HIMAMAYLAN CITY, NEGROS OCCIDENTAL

Region VI, Region VI

2021₱183.3M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION OF ROAD WITH SEAWALL, BARANGAY TABA-TABA TO BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE, B

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS DAANG MAHARLIKA (LZ),K0356+076-K0357+377.00; K0357+406-K0357+894.00; K0357+920.00-K0358+819.00, CAMARINES NORTE 2ND LEGISLATIVE DISTRICT

Region V, Region V

2020₱144.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, OFF-CARRIAGEWAY IMPROVEMENT, TERTIARY ROADS: JUBAN-MAGALLANES ROAD, JUBAN AND MAGALLANES, SORSOGON PROVINCE

Region V, Region V

2018₱139.7M
Reported complete (DPWH)
No sat.

CONST. OF CONCRETE ROAD - BRGY. SAN ANTONIO - CONDEZ - SAN LUIS - SAN VICENTE - FLORES ROAD LEADING

Region VI, Region VI

2017₱134.8M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CLUSTER V-I-REHABILITATION/IMPROVEMENT OF REVETMENT ALONG BARANGAY BAGACAY-PACO SECTION, BOTH SIDE

Region V, Region V

2021₱130.4M
Past target date (DPWH On-Going)
View all 736 projects →

4. Implementation

Contract Amount

₱67,667,693.00

Progress

Past target date (DPWH On-Going)

Start Date

March 15, 2023

Target End

May 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.