Buildings and Facilities17AI0346

CONSTN OF TWO STRY FOUR CL SB (WITH MICROPILE), SAN MIGUEL E/S, NATIVIDAD, PANGASINAN

CONSTN OF TWO STRY FOUR CL SB (WITH MICROPILE), SAN MIGUEL E/S, NATIVIDAD, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱11,022,611.40. Status: Reported complete (DPWH). Contractor on record: 2-R CONST AND SUPPLY. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,022,611.40

Progress

Reported complete (DPWH)

Start Date

December 18, 2017

Target End

September 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.