Roads24DD0255

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY IN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY IN is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱144,045,000.00. Status: Past target date (DPWH On-Going). Contractor on record: ALPHA VECTOR CONST AND SUPPLY 44630. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bawi and Banaba Creek, Padre Garcia, Batangas
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Batangas 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 44630

99 projects · ₱1.7B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, MANILA-BATANGAS - BUGTONG NA PULO - STAR TOLLWAY INTERCHANGE PACKAGE C, BUGTONG NA PULO, LIPA CITY, BATANGA

Batangas 4th DEO, Region IV-A

2024₱140.4M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- TERTIARY ROADS- CORON-BUSUANGA ROAD, K0059+866-K0061+205, CORON, PALAWAN

Region IV-B, Region IV-B

2023₱101.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANILA-BATANGAS - BUGTONG

Batangas 4th DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANABA BRIDGE BUSUANGA, PALAWAN

Palawan 1st DEO, Region IV-B

2024₱96.5M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF SLOPE PROTECTION STRUCTURE (KIWIT BR. 1), BUSUANGA, PALAWAN

Region IV-B, Region IV-B

2025₱72.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BUGTONG NA PULO ELEMENTARY SCHOOL, BARANGAY BUGTONG NA PULO, LIPA CITY, B

Batangas 4th DEO, Region IV-A

2025₱67.2M
Past target date (DPWH On-Going)
View all 99 projects →

4. Implementation

Contract Amount

₱144,045,000.00

Progress

Past target date (DPWH On-Going)

Start Date

September 9, 2024

Target End

July 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.