Buildings and Facilities17GI0139

CONSTRUCTION OF 1 UNIT-1STY2CL SCHOOL BUILDING, AGUTAYAN-LUPA ES, STA. BARBARA, ILOILO

CONSTRUCTION OF 1 UNIT-1STY2CL SCHOOL BUILDING, AGUTAYAN-LUPA ES, STA. BARBARA, ILOILO is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱2,785,970.77. Status: Reported complete (DPWH). Contractor on record: CLY - ABC BUILDERS. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,785,970.77

Progress

Reported complete (DPWH)

Start Date

January 8, 2018

Target End

April 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.