Roads17GG0110

CONCRETING OF BRGY. JNR CABUGAO NUEVO-BRGY. PALJE FMR, BRGY. CABUGAO NUEVO & PALJE, SAN ENRIQUE, ILOILO

CONCRETING OF BRGY. JNR CABUGAO NUEVO-BRGY. PALJE FMR, BRGY. CABUGAO NUEVO & PALJE, SAN ENRIQUE, ILOILO is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱1,860,151.34. Status: Reported complete (DPWH). Contractor on record: GGMU CONST AND SUPPLY. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱39,030,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
(Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers), along Jalaur River, Brgy. Imbang Pequeño, Sta. 0+000 - Sta. 0+359, San Enrique, Iloilo
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-17-0025289

₱1,049,184.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱1,860,151.34

Progress

Reported complete (DPWH)

Start Date

July 26, 2017

Target End

August 24, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.