Roads20FC0045

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS; DAET-TALOBATIB-JOSE PANGANIBAN MONUMENT (NATIONAL HERO) & BULALAKAO BEACH TO LARAP TO CAROLINE ISLAND TO BAGONG SILANG-CAPALONGA ROAD, ROAD LEADING TO PAG ASA BEACH TO LARA

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS; DAET-TALOBATIB-JOSE PANGANIBAN MONUMENT (NATIONAL HERO) & BULALAKAO BEACH TO LARAP TO CAROLINE ISLAND TO BAGONG SILANG-CAPALONGA ROAD, ROAD LEADING TO PAG ASA BEACH TO LARA is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱39,100,255.71. Status: Reported complete (DPWH). Contractor on record: BRENTMIN ROOFING ENT. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mercedes Flood Mitigation Structure, Brgy. II-Brgy. III, Mercedes, Camarines Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Norte DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

236 projects · ₱7.6B total · 5 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MOCONG, BASUD, CAMARINES NORTE, BASUD, C

Region V, Region V

2025₱240.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BASUD RIVER, BARANGAY MAMPILI, BASUD, CAMARINES N

Region V, Region V

2025₱240.1M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY MATOOGTOOG AND BARANGAY

Region V, Region V

2025₱234.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, MERCED

Region V, Region V

2024₱186.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF MITIGATION STRUCTURE ALONG CULASI RIVER, BARANGAY PAMBUHAN, M

Region V, Region V

2024₱176.9M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG

Region V, Region V

2024₱162.1M
Reported complete (DPWH)
View all 236 projects →

4. Implementation

Contract Amount

₱39,100,255.71

Progress

Reported complete (DPWH)

Start Date

December 1, 2020

Target End

May 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.