Construction of Flood Mitigation Structure22PB0004

Construction of Barren River (Upstream) Flood Control Structure, Sta. 39 + 693 - Sta. 39 + 893 (R/S), Brgy. Ili, Conner, Apayao

Construction of Barren River (Upstream) Flood Control Structure, Sta. 39 + 693 - Sta. 39 + 893 (R/S), Brgy. Ili, Conner, Apayao is a DPWH-tracked public work in CONNER (APAYAO), APAYAO, Cordillera Administrative Region. Reported contract value: ₱15,680,000.00. Status: Reported complete (DPWH). Contractor on record: BAHRAMLEY CONST. Figures trace to sumbong.

CONNER (APAYAO), APAYAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱16,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Barren River (Upstream) Flood Control Structure, Sta. 39 + 693 - Sta. 39 + 893 (R/S), Brgy. Ili, Conner, Apayao
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002926

₱213,677,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

1 projects · ₱15.7M total · 0 flags

4. Implementation

Contract Amount

₱15,680,000.00

Progress

Reported complete (DPWH)

Start Date

March 1, 2022

Target End

December 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.